 |
March 89, 2007
Kansas City Convention Center
Kansas City, Mo.
Sponsors
Presented by AIA Design-Build Knowledge Community
Prime Cosponsor: Associated Builders and Contractors
Shughart Thomson & Kilroy Law Firm
Lockton Companies
Skanska
Walton Construction
Myer Brothers Building Company
California Center for Construction Education
The Bannett Group Ltd. Design Builders
Agenda
Speaker Bios
To view the speakers' PowerPoint
presentations that are available, click on the title of the
corresponding conference session. In the case of multiple speakers,
please click on the individual speaker's name.
All photos courtesy of G. William
Quatman
Design-build can place
architects and design excellence in the lead of construction
projects.
The author of this conference report, Cindy
Frewen Wuellner, FAIA, is with Frewen Architects, Kansas City,
Mo., and is a University of Kansas doctoral candidate.
Overview
Will design-build transform the architecture profession? Further,
will traditional design-bid-build lose its long-held dominance of
the construction industry? Speakers at the Design-Build Summit said
yes to both questions. An increasing number of projects use
design-build project delivery and all but five states allow
design-build on public projects in some way. (See AIArchitect article). Now
architects have to evaluate how, not if, they
want to approach design-build.
.jpg)
Attendees enjoy some Kansas City
barbecue
Perceived limitations for project types and team members
roles are changing. Many people thought that design-build was
only appropriate for warehouses or parking garages. But its future
is in its potential for all project types, according to Bill
Quatman, FAIA, chair of the AIA Design-Build Advisory Group. He
cites the Chicago Public Library, Denvers Downtown Aquarium,
and Caltrans District 7 Headquarters in Los Angeles as design-build
exemplars. Further, more architects are participating. Currently,
more than 8,000 AIA members or approximately 10 percent of the
membership belong to the Design-Build Knowledge Community.
Extrapolated trends for design-build projects compared to
design-bid-build projects indicate that by 2010 an equal number of
projects will be completed by each. Beyond that point, design-build
will dominate the construction delivery
process.
The Design-Build Summit, held at the Kansas City Convention Center,
focused on architects best options within the realm of
integrated practice. The organizers emphasized areas that many
architects consider trouble spots, and that paradoxically offer the
best opportunities, namely design excellence and architect-led
projects. Several architects of award-winning design-build projects
testified they regained design control owing to more meaningful
interaction with construction specialists. A number of presenters
offered their approaches for architect-led design-build projects.
Architects leading design-build must reshape their practice to
encompass construction services. Consequently, risk participation
was a common theme. Brad Buchanan, FAIA, Buchanan Yonushewski Group
LLC, an architect who has completed several design-build projects
in Denvers downtown revitalization boom, summarizes the new
proactive position architects must take with their clients,
If youre in the room, youre in the deal. He
changed the way that he thought about design and construction by
accepting greater risk and therefore gained greater rewards. His
firm not only designs and builds, but helps arrange financing and
assembles investors.
Advisory Group
members Betsy Downs, AIA;
Bill Quatman, FAIA; and Barry Bannett
Many presenters see integrated practice as a transformational
change for architects. Responsibilities are no longer defined as
segregated service silos with distinct perspectives for
professional designers and contractors. Instead, the project team
members respect differences but develop alignments based on
completing the best possible project for the client. Harold Adams,
FAIA, chairman emeritus of RTKL Associates, goes one step further.
The current system is broken; 20 years ago, architects lost
the pedestal as the owners trusted representative.
During construction, the contractor takes control of the process
and has the clients ear. Adams believes that architects can
only regain credibility through integrated practice. Further, he
recommends bringing the entire team together from start to finish.
Mental shifts begin with education, according to Prof. Barbara
Jackson, PhD, California Polytechnic State University. The program
assembles integrated teams of architectural, engineering, and
construction management students to jointly develop projects and
learn side-by-side. Design-build represents a transformational
change to the profession because it requires fundamentally
different attitudes, responsibilities, and relationships.
Why should architects prefer design-build? Design
control, according to Juan Moreno, AIA, Ghafari Associates.
When design is a priority for the integrated design-build team, it
regains status. Gary Lapera, AIA, Michael Graves and Associates,
believes it is the most efficient way to deliver a building. Harold
Adams says, It gets us back to our traditional roles.
Three viable approaches emerged for firms. An architect can work as
a subcontractor with a trusted general contractor or developer. An
architect can assume a portion of risk as a financial partner. Or
an architect can lead the process by expanding in-house services.
Experts generally agreed that the architect could not lead when
providing only architecture services.
Judging by comments from audience members, design-build remains an
uncomfortable fit for some architects. However, a unified message
resounded from the symposiums leaders. Rather than confining
design-build to marginalized project types, the industry will soon
reach a tipping point. Each year, fewer projects will be available
by the traditional method. Through participating in the
evolution of design-build, architects can shape their role and
uphold the value of design by leading the process.
Opening Remarks
Rebekah G. Gladson, AIA, DBIA, 2007 chair, The Design-Build
Institute of America (DBIA), associate vice chancellor and campus
architect, University of California, Irvine
Two trends are aligning that favor design-build, according to
Rebekah Gladson. Over the next 20 years, 75 percent of buildings in
the United States will need to be built or rebuilt. Simultaneously,
members of the workforce who are older than 45 will be retiring;
those younger than 45 is a smaller group, resulting in fewer people
to produce a huge amount of design work. Gladson believes
design-build responds to the demand for more efficient production.
She urged architects to understand the differences between and
alignments with owners and contractors. As problem solvers in a
profession that strives for excellence, architects are positioned
to be leaders in design-build.
Session 1. Doing Great Design When Working for a
Contractor (presentation not available)
Gary Lapera, AIA, Michael Graves & Associates, Princeton,
NJ
Michael Graves
and Associates learned the necessary skills for design-build by
developing
industrial design products. Gary Lapera says buildings become a
massive customization, a kit of parts, a pattern for
living. Design-build enables a seamless process for design,
build, and marketing. Simultaneously, boundaries between
architects, developers, contractors, manufacturers, and technology
partners diminish. Lapera suggests that when architects think of
design-build, Think of the ideas you have and how this
process will allow you to bring this one idea to the
market.
Gary Lapera, AIA, explained how the design-build
process can produce great design
Design-build team members share common goals and experience
similar struggles but have different methods, agendas, and belief
systems. Rather than assume that design is everything and rules
decisions, the architects concepts have to stand up to the
rigors of others ideas during the building process. Based on
his experiences on the Netherlands Ministry of Health, Welfare, and
Sport and the National Museum of Automobiles in The Hague, plus
examples in Japan and the United States, Lapera made four
recommendations. First, create strong strategic partnerships by
selecting the right partners and work with them to build a
synergetic relationship that counts dollars from day
one. Second, establish a seamless, flexible communication
process using frequent meetings and technological solutions for
timely updates. Third, allow the design process to build momentum
that remains compelling in later phases. Fourth, see the potential
for design-build. Owners and users ultimately appreciate the final
design, but the process is a barrier for them. Lapera says,
Understand the entire product development process. How you
package it; how you create a sense of completeness. It all
matters.
Session 2. Why Architects Should Lead
Design-Build (presentation not
available)
Harold Adams, FAIA, RIBA, JAI, RTKL Associates Inc.,
Baltimore
The traditional design-bid-build system is broken,
according to Harold Adams. In the 1970s, lawsuits and risk-averse
insurance companies convinced architects to step away from
riska trend reflected in the AIA contract documents and
established strictly segregated roles. Furthermore, architects do
not know the cost of constructing their design solutions or exactly
how to detail construction projects. Calling architects the
paper representatives, and pointing out that
contractors are the ones who actually have the clients ear,
Harold Adams says, We have lost our credibility and our
ability to manage costs.
In design-build projects, the entire team works together from the
beginning. Adversarial positions disappear and the risk of
litigation is nearly eliminated while the client gets a faster
delivery process, a single point of responsibility, and reduced
change orders. However, a few problems exist. First, the upfront
costs for architectural design are high, so the architect has to be
compensated by the design-build partnership. Second, in
contractor-led teams, the contractor selects the architect, not the
owner. Finally, the architect loses contact with the client for
project decisions. However, good design adds value, and
therefore, the teams first responsibility is not to
save money, but to bring a project with added value.
Architects are the most qualified discipline to lead design-build
teams but need to develop new skills. Besides organizational
seminars and books, Adams suggests a few ways to get started.
1. Offer extended services to an existing client. Initially, RTKL
did interiors fit-up projects.
2. Create a specialtyRTKL did so by taking on a major
telecommunications project at the U.S. Capitol Building.
3. Learn from a contractor through a joint venture
partnership.
Adams believes universities are too structured by discipline and
would benefit by interdisciplinary project teams. Furthermore, he
believes, we are very shortchanged in our education.
Architects need to learn about finance, labor issues,
subcontracting, and bonding. We have been standing on the
sidelines with clean hands, we thought, as we allowed others to
take the lead. Adams believes architects can only regain
their position in the industry through a total integrated team
approach.
Session 3. The Next Level: Taking the
Lead in Design, Build, and
Development
Brad S. Buchanan, FAIA, Buchanan Yonushewski Group LLC,
Denver
Brad Buchanan thinks that architects have the mindset and are the
cultural leaders to lead design-build projects, but need to
learn all the pieces and parts. We need to know something about
everything. He has been in the center of Denvers
downtown Renaissance doing architect-led design-build including the
Dakota Lofts, Denver Square, and the Broadway Brewery adaptive
reuse. To lead design-build projects, Buchanan asks, Are you
entrepreneurial? How can you afford not to be? His drawings
are far simpler than traditionally bid projects but he spends more
time on site.
How does an architect get started? Buchanan recommends that
architects begin with baby steps. First, know several
bankers personally and track their real estate-owned properties
(REOs). In addition, be acquainted with real estate brokers, get
involved in the community, and learn basic financial planning
techniques. An HP business calculator provides an introduction to
pro formas. The AIA and AGC Design-Build Checklist is a useful tool
for teaming with contractors. Traditional relationships set up
architects and contractors for conflict. Through architect-led
design-build, the architect is the owners trusted advisor and
gains a marketing advantage plus serious cash flow
benefits.
Panel Question & Answer Session
Question: How often does bonding come up for architect-led
design-build projects?
Brad Buchanan says, Every single project, especially those
over $10 million. It is a limiter to our firms growth and
more of a limiter in the past five or six years because the market
shifted dramatically after 9/11. It forced us to keep cash in our
corporate entity. Buchanan says he looks for ways to reduce
the bonding requirements, such as breaking out portions such as
interior work or areas that could be bonded by subcontractors. Work
in progress reduces bonding capacity. He recommends developing a
strong relationship with the bonding company so that they might
increase the bonding capacity.
Angel Martinez, AIA, Martinez and Associates, a design-build firm,
says that public projects are always bonded and the lender
frequently requires private owners to get bonds. The owners see
bonding as the safest way to protect themselves from problems.
Rather than a blanket bond for the project, he recommends
identifying specific areas of risk that require bonding. Bill
Quatman says that dual obligee bonds were another option to
investigate, where the contractor provides the bond, which runs for
the benefit of the architect and the owner (the
obliges).
Lunch Presentations
The National World War I Museum at Liberty
Memorial
Stephen Abend, FAIA, PGAV Architects,
Westwood, KS
Kansas City Star Production
Facility (presentation not available)
Juan Moreno, AIA, Ghafari Associates, Chicago
Session 4. The Caltrans
District 7 Headquarters
Pavel Getov, Morphosis, Santa Monica, CA
The initial drawings for the California Department of
Transportation (Caltrans) District 7 Headquarters in Los Angeles
were done on a few napkins, and completion was guaranteed in 30
months, according to Pavel Getov. Despite these extraordinary
tactics, the LEED-certified building is recognized for its design
excellence and technological complexities for energy controls.
Getov likened the exterior skin to a European cuckoo clock where
each façade opens and closes separately in response to
environmental conditions. The design-build team was an association
of Morphosis and Clark Construction Group Inc. called Main and
First Design/Build Associates, Inc. A collaboration of architects,
engineers, contractors and manufacturers developed a 3D model that
merged design and shop drawings. Design was constantly negotiated
to find the most efficient means of construction. In other words,
the architect is involved in detailing means and methods that were
previously controlled by others. Getov said, This is not a
constraint; its a tool for the architect.
Rather than the large 30- to 100-member teams and 5 to 10 years
required for similar landmark projects, the Caltrans team consisted
of five to nine architects for 30 months. The design-build team was
designing, drawing, estimating, and building simultaneously, with
construction starting four months after project award. Getov
recommends that architects choose your bubble, that is,
be flexible and negotiate while maintaining design intent. For
example, an unsightly large truss arrived on site but rather than
reject it, they figured a way to conceal it. Other trade-offs aided
the design, such as the operable exterior skin cost more but
reduced heating and cooling systems. Since Caltrans moved into the
building in 2004, the department was recognized as the most
productive department in California. Getov notes, At least we
know the building is not distracting and may actually be
stimulating the workers. The 750,000-square-foot building
with 400,000 square feet of parking has two 13-story towers instead
of a single taller structure, houses 1,350 employees, and the
construction cost $170 million.
Session 5. Bridging and the
Architects Role as Owners
Consultant
George Heery, FAIA, RIBA, Brookwood Program Management LLC,
Atlanta
Handout
1
Handout 2
In the bridging process, the owner establishes two sets of
architectural roles. Because some confusion exists about bridging,
George Heery, its inventor, is very specific about the different
responsibilities. The Owners Design Consultant (ODC) takes
the design through design development, and these documents are the
basis for a design-build competition. The bid documents are
performance descriptions only and include preliminary engineering.
The second architectural/engineering team performs code compliance
and final design and engineering. The ODC continues through the
construction phase, approves payment applications, and reviews
drawings and construction for design compliance. The second
architect is the architect-of-record and works for the contractor
to supply the construction documents. Engineers may work for the
architect or for the contractor. Heery estimates the fee split
between the ODC and the architect-of-record is 65 percent versus 35
percent.
Through a bridging process, the owner gains a project design with a
fixed price in less time and less money with five to fifteen
percent savings. In addition, change orders are reduced. For the
architect, Heery says, Liability goes away. Most problems
occur because the general contractor has a claim against the owner.
Or if there is a design errorit goes away because the
design-build team works it out. General Services
Administration used this process on federal courthouse projects in
San Diego, Las Vegas, and San Francisco.
Heery created the bridging process because of serious flaws he
perceived in design-bid-build and design-build. Traditional
design-bid-build is predicated on a concept of perfect drawings,
which he notes, is humanly impossible. Obtaining a firm price for a
design takes too long. Plus design professionals do not have the
best construction knowledge; contractors do. On the other hand,
design-build integrates the team for single-point responsibility
and construction know-how during design, but it also creates
several disadvantages for the owner. The architect/contractor
collaboration sets up a conflict of interest between the
design-build team and the owner, the owners direct design
input shrinks, and apples-to-apples comparisons between project
proposals is difficult. Bridging solves these problems by directly
connecting the owner with the design architect.
Session 6. Challenges of Design-Build
in Sports Architecture
Joseph E. Spear, FAIA, HOK Sport + Venue + Event, Kansas City,
MO
Joe Spear learned three major lessons from design-build projects.
First, the contractor wants a scope set of documents, not a full
set. We could have done six sheets instead of 60.
Second, nuisance claims are virtually eliminated. Spear agreed with
Mr. Heery that in design-build, most claims simply go
away due to the collaborative process. While traditional
projects may have 6,000 requests for information, RFIs are not even
discussed in design-build because there is no payday for the
contractor. Finally, the architect can ask a subcontractor
for construction input rather than do unnecessary research.
Partnering with the contractor simplifies these relationships.
Spear cited three case studies they had completed using
design-build: The Phoenix Cardinals Stadium (NFL), Busch Stadium in
St. Louis (MLB), and Nationals Park in Washington, D.C.
(MLB).
Spears recommendations for a successful design-build project
involve relationships and communication. Project teams should have
previous experience working together, gain commitment from each
stakeholder, agree on objectives and expectations up front, create
a simple organizational structure, and develop clear and open
communication methods. Spear sees more onus clauses that mandate
fixed schedules and budget and more owners asking about
design-build, so HOK Sport is preparing for an increased number of
design-build sports facilities.
Session 7. Educating Architects for Design-Build
Delivery
Prof. Dan Rockhill, Studio 804, School of
Architecture & Urban Design, University of Kansas, Lawrence,
KS
Prof. Barbara J. Jackson, PhD, DBIA, California Center for
Construction Education, Cal Poly State University, San Luis Obispo,
CA
Two nationally recognized university programs offer very different
approaches to teaching design-build. At the University of Kansas,
Studio 804 architectural students design and construct a house in a
semester. The California Center for Construction Education program
blends cross-disciplinary teams of design and construction
management students to develop design-build project plans.
Studio 804 led by Dan Rockhill combines student engagement with
cutting-edge issues: design-build, prefabricated construction,
community involvement, and sustainable practices. After discovering
students enthusiasm for hands-on construction, a capstone
design studio was converted to a design-build experience. Students
make decisions democratically and complete design in January with
occupancy before May graduation. Several houses were built in
Lawrence, Kans., and the last three sites shifted to Kansas City,
Kans. To minimize site commutes, the buildings are primarily
constructed in a warehouse and moved in late April. Recycled
materials such as a hardwood gym floor and a redwood cooling tower
have been incorporated into the high-performance energy efficient
structures. The national award winning houses have ranged from
$75,000 to $155,000 in urban neighborhoods and have a buyers'
waiting list.
Rockhill says part of the objective is to push the design envelope,
despite occasional negative editorials. If we dont do
it, who does? The next direction is even greater socially
responsible projects, such as a yearlong community project.
We live in a very pampered society; the students love the
responsibility. After graduating, many seek jobs with
design-build firms. Although they could learn construction by
working for a contractor, Studio 804 allows them to actually
realize a design idea by building their own
concept.
The construction management program directed by Barbara Jackson
integrates architectural, architectural engineering, and
construction management students into teams. She says, Once
the students cross disciplines in a collaborative, integrative
process, they are spoiled. In 10-week projects, the students
learn interdisciplinary fluency and the impact of their decisions
on other disciplines. They work in War Rooms, instead
of classroomsopen office spaces with four-person cubicles
shared by team members, somewhat like architecture studios.
The current Gen X students are well-suited to design-build,
according to Jackson. The students actually demand
change, she says. She characterizes the cohort group as
inclusive, problem solvers that seek involvement and use text
messaging more than face-to-face meetings. The students in this
program want their projects to be about something other than
themselves. A recent project was a Clean and Sober facility
where they developed the design, estimate, schedule, management
plan, and value engineering. During an intensive 16-hour
competition, students created a design and management plan for an
$84 million facility. Instead of focusing on individual efforts,
Jackson says the students come to the table to discover a
solution.
Professional Practice Breakout Sessions
1. Making the Transition from Designer to
Design-Builder
Prof. Barbara J. Jackson, PhD, DBIA,
California Center for Construction Education, Cal Poly State
University, San Luis Obispo, CA
J. Angel Martinez, AIA, Past Chair,
Design-Build Advisory Group, Martinez and Associates, Overland
Park, KS
In Barbara Jacksons mind, at a typical design-bid-build
meeting, designers and builders have their antennas raised to
detect, How are you going to mess with my time, my cost, or
my design. In contrast, design-build teams focus on the
project and solving problems. The NO GAPS team creates
a fit between owners expectations and the delivered project.
When a concern arises, the response is not blaming or denial.
Instead, members say, Okay, I got it; tell me more.
Problem solvers are forward focused, use non-confrontational
questions, and have the ability to extract another persons
needs from the interaction. The question, not the answer, is
central. Jackson says, Great results begin with great
questions. Design-build team members are curious learners,
not protective judgers. In sum, they value inquiry rather than
knowing, flexibility, and both/and instead of either/or.
As an architect whose firm also builds, Angel Martinez takes a very
practical view of architects becoming design-builders. Why
not be builders? he asks rhetorically. If concerned about
enough money or bonding capacity, Martinez reminds architects that
builders also did not have money or bonding when they started. He
believes that building makes architects better designers. The
primary considerations are responsibility and control.
Architects think the contractor has the risk; the architect
has no control. But the drawings are on site. In other words,
architects already have risk. He believes architects can better
serve clients as design-builders. They need to acquire business
skills plus knowledge of construction such as scheduling,
coordinating, estimating, and job safety. Martinez recommends that
architects keep the administration simple, offer excellent benefits
to attract and retain quality employees, and carefully manage cash
flow issues. He sees architects as the best leaders for
design-build teams with three possible avenues: within a
construction firm (employee), as a subconsultant to general
contractors, or as an integrated designer-led contractor. To
complete excellent design-build projects, he says, You can
make an architect a project manager, but not the other way
around.
2. Architect as Prime Design-Build
Contractor
Martin E. Sell, AIA, Design-Build Advisory Group Member,
Horizon Design-Build-Manage, Madison
Betsy Downs, AIA, DBIA, Design-Build Advisory Group Member,
OWP&P, Chicago
Martin Sell warns architects, If you want to survive, you are
going to have to change. And if you dont, youre going
to perish. Its as simple as that. He has tried a couple
of models for design-build. During a 14-year contract with the
Beaver Dam Unified School District in Wisconsin, his firm did the
design and construction management, using subcontractors for
construction. Design represented 40 percent of the work,
construction 40 percent, and administrative overhead 20 percent.
His second model was water park resort hotels, or riches in
the niches, where he developed a strategic relationship with
a specialty aquatic firm. The cost allocations shifted to 15
percent design, 15 percent development, and 60 percent construction
and general conditions. His firm does not self-performed
construction work and they will not do strictly architectural
projects. They are licensed as a general contractor and as an
architect in multiple states. Sell urges architects to use
architectural design as a method for selling design-build
projects.
Betsy Downs believes in working with trusted contractor partners to
deliver integrated services rather than with subcontractors. To be
able to respond quickly to design-build opportunities, her firm has
teaming agreements with 19 general contractors. They work primarily
with three of those firms. They use AGC forms and are licensed as a
general contractor in four states. Their design-build projects are
typically health care, education, or corporate commercial
facilities.
3. What Contractors Want from their
Architect-Teammate
Jim L. Whitaker, AIA, Skanska USA Building Inc.,
Charlotte
Jeff Turk, DBIA, Walton Construction, Kansas City, MO
Presenting from a contractor-led design-build perspective, Jeff
Turk described the architects role in design-build projects
as a proverbial paradigm shift. He says, You are
not the owners watchdog anymore. Good design-build team
members focus on project goals for quality, budget, and schedule,
and act as learners, not as knowers. For optimal teams,
architects and contractors should co-locate and begin with a
brainstorming session to create common project objectives. Although
Turk thinks that compensation should be similar to traditional
architecture fees, he itemized a number of changes in services.
Design-build projects need fewer drawings and specifications, and
less architectural involvement during construction administration.
Instead of written requests for information, e-mails and
conversations resolve issues more quickly. If there are mistakes on
the drawings, the architect needs to fix these without
compensation. Two hours of redrawing is cheaper than a jack
hammer. Financial rewards are only shared if the risk of any
cost overruns is also shared.
Open communication and constructive conflict are essential between
the contractor and the architect while other relationships are
controlled through the contractor. Engineers may work for the
mechanical or electrical contractor so the architect must consult
with the contractor before committing to solutions. Similarly,
creative staff cannot take ideas directly to the owner
without authorization. Turk cautioned that certain damaging
statements should be avoided. Silence is a killer; Not
my job is a killer; I could have told you
that, represent the wrong approach. Problems should be
addressed within the team, not with the owner, and mistakes should
be acknowledged and remedied quickly. He says, Blaming is a
waste of time. In sum, Architects must understand that
time is money.
Other Breakout Sessions
1. Insurance and Bonding Demystified for
Design-Build
Handout
Brian Dooley, Lockton Companies
Barry Bannett, AIA, DBIA, Design-Build Advisory Group Member, The
Bannett Group Ltd.
2. Educators Forum
Prof. William J. Carpenter, FAIA, PhD, Member, AIA Design-Build
Advisory Group, Southern Polytechnic State University
Prof. Dan Rockhill, Studio 804, University of Kansas
3. Using Design-Build on K-12 Schools
Benjamin K. Wilking, AIA, DBIA, Past Chair,
Design-Build Advisory Group, LBA Corporate Services
David Engdahl, AIA, DBIA, The Haskell Company
Facility Tours
The National World War I Museum at Liberty
Memorial Reception and Tour
Stephen Abend, FAIA, PGAV Architects, Westwood, KS
Located in
Penn Valley Park overlooking Union Station and downtown Kansas
City, the Liberty Memorial is a 1921 art deco monument designed by
H. Van Buren Magonigle. According to Stephen Abend, FAIA, lead
architect for the renovation and exhibit expansion, a visit to the
Acropolis-like structure is an emotional experience. Past a pool
and waterfall, through massive bronze entrance doors, a lobby
skylight frames a view of the 217-foot tall limestone obelisk on
the exterior deck above. Visitors walk over a clear glass bridge
spanning a symbolic poppy field to access the exhibit, designed by
Ralph Appelbaum Associates. The renovation of the memorial was
completed in 2002. The design-build expansion for museum exhibit,
completed by ASAI Architects and Turner Construction, opened in
December 2006.
Dr. A.A. "Manny" Sultan, architect with
AAS Associates International
(Tokyo, Japan) and his wife Yasuko, with 2007 DBIA chair Rebekah
Gladson,
AIA, DBIA, and Barry Bannett, DBIA, vice-chair of the AIA
Design-Build Advisory Group
Kansas City Star Production
Facility Presentation and Tour
Juan Moreno, AIA, Ghafari Associates, Chicago
Juan Moreno,
AIA, gave a tour of the Kansas City Star
production facility, a $200 million design-build project
Founded more than 100 years ago, The Austin Company was the first
design-build firm, according to Juan Moreno, former lead designer
at Austin. Moreno turned the building inside out so
that passersby could watch the presses roll on the state-of-the-art
color printing presses. A tilted glass
curtain wall at the north end is anchored by horizontal bands of
copper cladding, contrasting machine scale with human scale. The
Kansas City Star was committed to a downtown location and selected
a two-block Crossroads District site adjacent to their 1911
headquarters designed by Jarvis Hunt. A raised section near the
center reflects the Italianate Renaissance-style tower of the
original facility. Moreno worked with A. Zahner Sheet Metal to
determine the most cost-effective copper panel size and to develop
the unique green patina. The $200-million design-build project is
424,000 square feet, meets LEED Silver sustainable design
requirements, and opened in June 2006.
A. Zahner Sheet Metal
Tour
Robert Zahner, Tom Zahner, & Roger Reed, A. Zahner Sheet
Metal, Kansas City, MO
.jpg) .jpg) .jpg)
Attendees tour A. Zahner Sheet Metal |
A. Zahner is a fourth-generation sheet metal fabricator that
shifted to building high-performance skins during the last two
decades. Notable projects include Gehrys Jay Pritzker
Pavilion at the Millennium Park in Chicago and Ericksons
Museum of Glass in Tacoma. The tour followed the development of an
exterior panel system for a Massachusetts store through design
engineering, shop work, and to the yard where sections were being
shipped. Zahner is using advanced 3D modeling programs such as
Pro/Engineer, CATIA, and Rhino 3D to reshape architectural forms
within allowable stress ranges. Sections out of compliance are
color highlighted so the designers can play with the 3D form until
it meets the materials capacity. For particularly complex
structures, design architects office at Zahner to work with
in-house design professionals. In the shop, a new oversized flatbed
waterjet cutter was slowly shaping a metal art piece. In the yard,
along with the sections headed for the department store sat various
parts from Libeskinds Contemporary Jewish Museum in San
Francisco, Gehrys Ohr OKeefe Museum of Art in Biloxi,
Miss., and Pellis Tulsa Arena. One architect wondered whether
Zahner had built an edge that eliminated competition. Roger Reed
says they are deeply grounded in the fundamentals of sheet metal
sub-contracting, and through continual improvements over time,
created a specialty. With a history of innovation (his father, Leo
Zahner, is credited with creating the first SMACNA Manual), Zahner
grew into an integrated practice, developing design, construction,
and communication processes.
|